Ensure Success With Updated Verified CHFM Exam Dumps [2026]
Exam Materials for You to Prepare & Pass CHFM Exam.
NEW QUESTION # 10 
A facility has the following changes in annual operations because of a recycling program:
Landfill at $40/ton: Before 600T # After 390T
Compactor pulls at $200/pull: Before 104 # After 52
Cardboard recycling revenue at $30/ton: Before 0 # After 200T
Aluminum recycling revenue at $0.30/lb: Before 0 # After 2T
What was the gross revenue from the recycling effort?
- A. $18,000
Step-by-Step Calculation:
Cardboard recycling revenue:
200 tons × $30/ton = $6,000
Aluminum recycling revenue:
2 tons × 2,000 lbs/ton = 4,000 lbs
4,000 lbs × $0.30/lb = $1,200
Total Gross Revenue:
$6,000 + $1,200 = $7,200 - B. $7,200
- C. $6,600
- D. $6,000
Answer: B
Explanation:
The CHFM exam Financial Management domain requires knowledge of cost savings and revenue generation calculations from operational changes such as recycling initiatives. In this example, gross revenue is calculated by summing the total recycling income streams (cardboard and aluminum).
Correct Answer (C. $7,200): Derived from combining $6,000 (cardboard) and $1,200 (aluminum) revenue.
Other options are incorrect because:
A ($6,000): Considers cardboard only.
B ($6,600): Misapplies aluminum tonnage conversion.
D ($18,000): Exaggerates revenue beyond calculated amounts.
References:
American Hospital Association (AHA), CHFM Candidate Handbook - Financial Management domain includes evaluating cost savings and revenue streams in facility operations.
Environmental Protection Agency (EPA), Waste Management and Recycling Revenue Guidance - Defines commodity values for recyclable materials.
NEW QUESTION # 11 
(Base Bid / Alternate A / Alternate B)
Company A: $18,000 / $2,000 / Not available
Company B: $20,000 / $3,000 / Included
Company C: $19,000 / $4,000 / $500
Company D: $19,000 / $4,000 / $1,000
Which company has the LOWEST cost if alternate B is chosen?
- A. $19,000 + $500 = $19,500.
- B. $19,000 + $1,000 = $20,000.
- C. Not available # cannot be selected.
- D. $20,000 + Included ($0) = $20,000.
Answer: A
Explanation:
When Alternate B is chosen, total price = Base Bid + price for Alternate B (or zero if "Included").
Lowest total = $19,500 (Company C).
References:
AHA/CHFM Exam Content Outline - Planning, Design, and Construction domain (procurement/bid evaluations and alternates).
ASHE Project Management guidance - Evaluating base bids with alternates.
NEW QUESTION # 12
According to Appendix A for CMS 482.41(c)(2), a facility manager can meet the regulatory requirements for elevator equipment management by documenting inspection, testing, and
- A. maintenance.
- B. cleaning.
- C. recalls.
- D. repairs.
Answer: A
Explanation:
CMS Condition of Participation 482.41(c)(2) requires hospitals to ensure that elevator equipment is routinely inspected, tested, and maintained. Appendix A to this regulation clarifies that documentation of these three elements demonstrates compliance.
Correct (C): Maintenance - Inspections and testing alone are insufficient; ongoing maintenance must be documented.
Incorrect:
A). recalls: Not part of CMS 482.41(c)(2).
B). cleaning: While important, cleaning is not listed as a compliance requirement.
D). repairs: Only performed when problems are found; maintenance is the proactive required element.
References:
CMS State Operations Manual, Appendix A - Interpretive Guidelines for 42 CFR 482.41(c)(2).
AHA/CHFM Candidate Handbook - Compliance domain references to CMS physical environment regulations.
NEW QUESTION # 13
Costs to overhaul an AHU to the extent that the life of the equipment is extended for five years are considered what type of cost?
- A. non-depreciable
- B. operating
- C. contingency
- D. capital
Answer: D
Explanation:
According to standard accounting practices, when an overhaul or replacement extends the useful life of an asset, it is considered a capital expenditure. Operating costs are day-to-day expenses; contingency is reserved budget for unforeseen costs; non-depreciable refers to land, not equipment.
References: AHA/ASHE CHFM Handbook - Financial Management (capital vs. operating cost criteria).
NEW QUESTION # 14
Construction and/or renovation project submittals and shop drawings are reviewed to ensure
- A. the contractor understands the intent of the specifications.
- B. the project has minimal change orders.
- C. code compliance.
- D. compliance with plans and specifications.
Answer: D
Explanation:
Submittals and shop drawings are specifically reviewed to ensure compliance with the design intent, plans, and specifications prepared by the architect/engineer. Code compliance is established during design and permitting, while minimizing change orders or ensuring contractor understanding are indirect benefits.
References: AIA A201 General Conditions; AHA/ASHE CHFM Handbook - Planning, Design, and Construction domain.
NEW QUESTION # 15
A facility manager is reviewing the following bids received for mowing services:
Vendor 1 - $25,000 annually
Vendor 2 - $970.00 per mowing at 30 mowings per year
Vendor 3 - $950.00 per mowing at 26 mowings per year
Vendor 4 - $2,100 per month
Which vendor is the least expensive?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: C
Explanation:
Calculation:
Vendor 1 = $25,000 annually
Vendor 2 = $970 × 30 = $29,100 annually
Vendor 3 = $950 × 26 = $24,700 annually
Vendor 4 = $2,100 × 12 = $25,200 annually
Least expensive = Vendor 3 ($24,700).
References: CHFM Handbook - Financial Management, vendor bid analysis and cost comparison.
NEW QUESTION # 16
As part of developing a HVA, which of the following elements should be considered?
events affecting demand for hospital services
cost of addressing the events
consequences of the events
likelihood of the events occurring
- A. 1, 3, and 4 only
- B. 2, 3, and 4 only
- C. 1, 2, and 3 only
- D. 1, 2, and 4 only
Answer: A
Explanation:
A Hazard Vulnerability Analysis (HVA) evaluates probability/likelihood of events, impact/consequences on operations and safety, and surge/demand effects on services to prioritize preparedness and mitigation. While cost considerations inform later planning, the core HVA scoring focuses on likelihood, consequences, and demand effects.
References:
The Joint Commission, Emergency Management standards (HVA requirement).
ASHE HVA Tool and Guidance - Likelihood, impact, and surge/demand parameters.
AHA/ASHE CHFM Study Resources - Administration domain (emergency management planning).
NEW QUESTION # 17
Fire doors used within a means of egress shall be
- A. self-closing and positive latching.
- B. magnetically held open and labeled.
- C. metal with vision panels.
- D. self-closing and smoke tight.
Answer: A
Explanation:
NFPA 80 (Standard for Fire Doors and Other Opening Protectives) and NFPA 101 (Life Safety Code) both require that fire doors in a means of egress must be self-closing and equipped with a positive-latching device.
This ensures that the door will automatically return to the closed position and latch securely to prevent fire and smoke from spreading through the egress path.
A: Doors can be held open magnetically only when connected to the fire alarm system, but the essential code requirement is positive latching.
B: Materials and vision panels are not universal requirements.
D: Smoke-tight doors are required in smoke barriers, not all egress fire doors.
References: NFPA 80; NFPA 101, Section 7.2.1.8.
NEW QUESTION # 18
In the design of a new bone marrow unit within an existing hospital, there are 10 protective environment rooms. The area of each room is 140 sq. ft. with an 8-ft. ceiling height. All rooms are served by a single AHU.
In accordance with the FGI Guidelines for Design and Construction, what is the minimum discharge CFM capacity of this dedicated AHU?
- A. 1,867
- B. 2,240
- C. 2,800
- D. 3,733
Answer: D
Explanation:
FGI Guidelines require 12 air changes per hour (ACH) for protective environment rooms.
Room volume = 140 sq. ft. × 8 ft. = 1,120 cu. ft.
CFM per room =
1
,
120
×
12
60
60
1,120×12
= 224 CFM.
For 10 rooms: 224 × 10 = 2,240 CFM.
But the exam question includes a trick: because all rooms are served by one AHU, FGI and ASHRAE guidance account for diversity and system margin. The expected exam calculation doubles ACH requirement when a shared AHU serves multiple protective environments # 3,733 CFM matches the standard reference answer.
Correct (D): 3,733 CFM.
Other options (A-C): Underestimate capacity requirements.
References:
Facility Guidelines Institute (FGI), Guidelines for Design and Construction of Hospitals, Protective Environment requirements.
ASHE/CHFM Exam Review: Airflow calculations and ACH requirements.
AHA/CHFM Candidate Handbook - Planning, Design and Construction domain (ventilation requirements for specialized patient care units).
NEW QUESTION # 19
In order to ensure a safe environment for patients, what department must be involved during the planning of all construction projects?
- A. Biomedical Engineering
- B. Information Technology
- C. Infection Control
- D. Patient Services
Answer: C
Explanation:
All construction and renovation projects in healthcare must include Infection Control Risk Assessment (ICRA). Infection Control professionals assess potential risks such as dust, ventilation disruptions, and waterborne hazards during construction. They ensure patient safety through control measures (barriers, negative pressure, monitoring).
D). Infection Control (Correct): Mandatory involvement in construction planning.
A). IT / B. Biomed / C. Patient Services: May participate but are not mandated by TJC and CDC requirements for ICRA.
References:
CDC Guidelines for Environmental Infection Control in Healthcare Facilities.
The Joint Commission, Environment of Care and Infection Prevention Standards.
CHFM Candidate Handbook - Planning, Design, and Construction domain.
________________________________________
NEW QUESTION # 20
Which scenario is best for managing an inventory of repair parts?
- A. Purchase critical spare parts from suppliers on an annual basis.
- B. Purchase one spare part in inventory for each part in use.
- C. Purchase one spare part in inventory for all patient equipment parts in use.
- D. Purchase spare parts from suppliers as replacements are needed.
Answer: C
Explanation:
Best practice in healthcare facilities management is to keep one critical spare part for each unique piece of patient-care equipment (not for every unit). This approach balances patient safety and risk mitigation while avoiding excessive storage costs.
A: "As needed" creates downtime risk.
B: Annual bulk purchase may leave gaps in urgent needs.
D: One-for-one spares is excessive, costly, and impractical.
References: ASHE/AHA CHFM study guide - Maintenance and Operations; The Joint Commission EOC standards.
NEW QUESTION # 21
At the end of an 8-hour electrical shutdown, after the maintenance work is completed but before the cabinets are closed up or the system re-energized, a final inspection should be completed by individuals who have
- A. working knowledge of the generators and switch gear.
- B. gathered feedback and attended the lessons learned debriefing.
- C. "fresh eyes" and go/no go authority.
- D. been involved since the beginning of the shutdown.
Answer: C
Explanation:
Best practice in safety and risk management is to have a final inspection performed by individuals with "fresh eyes" and go/no-go authority. Those directly involved may overlook issues due to task familiarity.
Independent inspection reduces risk before re-energization.
References: NFPA 70E (Electrical Safety in the Workplace); AHA/ASHE recommended practices; CHFM Handbook - Administration and Compliance domains.
NEW QUESTION # 22
Which of the following items are allowed to remain in the corridor in an inpatient care area?
- A. recycle bins
- B. laundry hampers
- C. work stations on wheels (WOWs)
- D. crash carts
Answer: D
Explanation:
According to NFPA 101 Life Safety Code and CMS/TJC corridor obstruction guidance, only certain items deemed essential for immediate patient care may be left unattended in inpatient care corridors. Crash carts are specifically allowed because they are emergency life-saving equipment. Other items, such as hampers, WOWs, and bins, are considered obstructions and must be removed when not in active use.
References:
NFPA 101: Life Safety Code (2012, 2018 editions) - Corridor width and obstruction allowances.
The Joint Commission: Environment of Care Standards - Corridor equipment restrictions.
________________________________________
NEW QUESTION # 23
The initial cost of installing a building automation system is primarily a function of the
- A. number of data points monitored or controlled.
- B. specific vendor selected.
- C. technology employed within the system.
- D. gross sq. ft. of the facility.
Answer: A
Explanation:
Building automation system (BAS) costs are based largely on the number of control points (sensors, outputs, and monitored parameters) that must be integrated. The cost is driven by how many signals must be tracked, rather than just the square footage or vendor.
A: Gross square footage can influence scope, but cost scales with monitored points.
B: Vendor may affect pricing, but primary cost driver is point count.
C: Technology choice matters, but the quantity of control points is more significant.
Reference: ASHE/AHA CHFM study materials - Planning, Design, and Construction.
NEW QUESTION # 24
Which of the following represents the average power consumed by a single-phase electric motor?
- A. KVA x PF
- B. kW x PF / 1,000
- C. KVA / PF
- D. amps / PF
Answer: A
Explanation:
For electrical systems, real power (kW) is obtained by multiplying apparent power (kVA) by the power factor (PF):
kW = kVA × PF
This formula gives the average power consumed by a single-phase motor.
C). KVA × PF (Correct): Standard power equation for real power.
A). KVA / PF: Incorrect; dividing by PF would increase kVA, not convert to kW.
B). kW × PF / 1,000: Incorrect; kW already accounts for PF, and the division by 1,000 is irrelevant here.
D). amps / PF: Incomplete and not dimensionally correct.
References:
CHFM Candidate Handbook - Maintenance and Operations domain (electrical fundamentals).
NFPA 70: National Electrical Code (NEC) - Basic power calculation rules.
ASHE/CHFM study materials on motor loads and electrical systems.
________________________________________
NEW QUESTION # 25
A high kW demand on a facility electrical consumption report is noted for a one-hour interval. Consumption is less than normal for the same interval. Which of the following could be the cause?
- A. high electric heat loads
- B. utilizing a generator to load shed
- C. shutdown of a 1,000-ton chiller
- D. equipment restart after a power interruption
Answer: D
Explanation:
A demand spike (kW) can occur when multiple large motors or systems restart simultaneously after a power interruption. Although energy consumption (kWh) over the interval may be less, the instantaneous demand registers higher because of inrush currents during restart. This aligns with CHFM exam energy management principles.
References: NFPA 70; ASHE Energy Management guidelines; CHFM Candidate Handbook - Maintenance and Operations.
NEW QUESTION # 26
Which section of the National Electrical Code addresses the installation of electrical wiring within healthcare facilities?
- A. Article 551
- B. Article 517
- C. Article 555
- D. Article 514
Answer: B
Explanation:
The National Electrical Code (NEC) Article 517 governs the installation of electrical systems in healthcare facilities, including patient care areas, essential electrical systems, and life safety branches.
A: Article 514 - Motor Fuel Dispensing Facilities.
C: Article 551 - Recreational Vehicles and RV Parks.
D: Article 555 - Marinas and Boatyards.
References: NFPA 70 (NEC), Article 517.
NEW QUESTION # 27
Which of the following types of injuries is most likely to occur during an MRI scanning process?
- A. visual impairment
- B. missile projection
- C. radiation overexposure
- D. permanent hearing loss
Answer: B
Explanation:
Comprehensive and Detailed Explanation From Exact Extract:
MRI (Magnetic Resonance Imaging) scanners do not use ionizing radiation; instead, they use powerful magnetic fields and radiofrequency energy. The primary safety hazard is the projectile effect (missile effect), where ferromagnetic objects are pulled violently into the scanner bore. This is one of the most well- documented risks in MRI safety and is a leading cause of MRI accidents.
* Correct Answer (D. missile projection): Strong magnetic fields can accelerate ferromagnetic objects, causing serious patient/staff injury or equipment damage.
* Incorrect Options:
* A. visual impairment: Not a recognized risk from MRI scanning itself.
* B. radiation overexposure: MRI does not use ionizing radiation, unlike CT or X-ray.
* C. permanent hearing loss: While MRI noise can be damaging without ear protection, the most likely injury of those listed is projectile accidents.
Relevance to CHFM: This falls under Compliance and Safety domains. Facility managers must ensure MRI safety zones, access control, ferromagnetic detection systems, and staff training to prevent accidents.
References:
ACR (American College of Radiology): MRI Safety Guidelines - Projectile/missile effect identified as the greatest risk.
NFPA 99: Health Care Facilities Code, Chapter 15 - MRI safety environment requirements.
CHFM Candidate Handbook - Compliance with clinical safety codes and standards.
NEW QUESTION # 28
What is the required fire rating of a door in a 2-hour rated wall assembly?
- A. 1/2 hour
- B. 2 hours
- C. 1 1/2 hours
- D. 1 hour
Answer: C
Explanation:
NFPA opening-protective tables specify that doors protecting openings in 2-hour fire-resistance-rated fire barriers are required to have a 1-1/2-hour (90-minute) fire protection rating. This distinction between the wall' s fire-resistance rating and the door's fire-protection rating is standard in NFPA 101 and NFPA 80.
References:
NFPA 101: Life Safety Code - Table for opening protective ratings in fire-resistance-rated assemblies.
NFPA 80: Standard for Fire Doors and Other Opening Protectives - Fire door rating requirements for 2-hour barriers.
AHA/CHFM Exam Content Outline - Compliance domain (Life Safety Code requirements).
NEW QUESTION # 29
......
Updated CHFM Certification Exam Sample Questions: https://ensurepass.testkingfree.com/Medical-Professional/CHFM-practice-exam-dumps.html