The PSP Certification Exam is designed for individuals who have experience in planning and scheduling and wish to validate their knowledge and skills in this field. Planning & Scheduling Professional (PSP) Exam certification is recognized globally and demonstrates a professional's proficiency in project planning and scheduling.


The AACE-PSP Certification Exam is designed to test the skills and knowledge required to be a successful project planning and scheduling professional. By earning the certification, professionals demonstrate their commitment to their career and their ability to apply the best practices and techniques in their work. Planning & Scheduling Professional (PSP) Exam certification provides professionals with a competitive edge in the job market and opens up new career opportunities. Additionally, the certification helps organizations identify professionals who are capable of delivering successful projects on time and within budget.

 

NEW QUESTION # 37
Why does activity 11001 not show successor activities?

  • A. It is the penultimate work required for the project
  • B. The early finish and late finish are circular
  • C. The scheduler forgot to add the successor activities
  • D. It is the final activity for the required work for the project

Answer: D


NEW QUESTION # 38
Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

  • A. The project geotechnical report
  • B. The government's report on future high-clearance bridge projects
  • C. The regulations published by the government aviation agency
  • D. The project plans and specifications

Answer: B


NEW QUESTION # 39
Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?

  • A. Packaging only.
  • B. Printing the Manual.
  • C. Testing, Manufacturing and Packaging.
  • D. Drafting and Proofing the Manual.

Answer: C


NEW QUESTION # 40
What is the workweek period for this project?

  • A. Monday through Friday
  • B. Sunday through Friday
  • C. Monday through Saturday
  • D. Sunday through Saturday

Answer: D


NEW QUESTION # 41
What is the actual duration as of the status date or data date of Activity B?

  • A. 4.
  • B. 3.
  • C. 7.
  • D. 0.

Answer: B


NEW QUESTION # 42
What does the narrow band at "Y" represent?

  • A. You cannot tell with the information supplied.
  • B. Resource limitation period.
  • C. A rework period.
  • D. Activity inactivity.

Answer: D


NEW QUESTION # 43
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?

  • A. B.
  • B. S.
  • C. C.
  • D. W.

Answer: B


NEW QUESTION # 44
When resource leveling craft labor for a critical path schedule, the scheduler

  • A. Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.
  • B. Need not consider its effects, as it is a theoretical concept with limited application to construction projects.
  • C. Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.
  • D. Need only consider the non-union crafts persons.

Answer: A


NEW QUESTION # 45
Activity C is a

  • A. Contentious activity.
  • B. Continuous activity.
  • C. 1-day activity.
  • D. Milestone.

Answer: D


NEW QUESTION # 46
What is the cycle time?

  • A. 5 minutes
  • B. 14 minutes
  • C. 17 minutes
  • D. 6 minutes

Answer: C


NEW QUESTION # 47
Under which circumstance should one perform resource-leveling calculations?

  • A. When the schedule is resource-loaded.
  • B. Never, unless required by the contract.
  • C. When the contract contains a provision for float-banking.
  • D. When you believe that known resource limitations may override schedule logic.

Answer: D


NEW QUESTION # 48
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?

  • A. Use the progressed portion of the critical path of all the updates previous to the current update.
  • B. Use the forward-looking critical path of the most current updates.
  • C. Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.
  • D. Use the progressed portion of the critical path of the baseline schedule.

Answer: B


NEW QUESTION # 49
If Activity E's duration changes to 4 months, what is the overall duration of the project.

  • A. 20 months.
  • B. 21 months.
  • C. 22 months.
  • D. 19 months.

Answer: A


NEW QUESTION # 50
How much Total Float does drafting the product manual have?

  • A. 0 workdays.
  • B. 5 workdays.
  • C. 10 workdays.
  • D. 15 workdays.

Answer: C


NEW QUESTION # 51
The work breakdown structure is used to organize

  • A. "Smart activity ID codes" representing similar items of scheduled work
  • B. The chart of accounts
  • C. The smallest defined work packet
  • D. Similar activity coding of schedule activities

Answer: C


NEW QUESTION # 52
Time-scaled logic diagrams are

  • A. Used to calculate the most probable activity duration.
  • B. Logic networks that are drawn to match the calendar.
  • C. The same as a pure-logic diagram.
  • D. Only calculated using a computer.

Answer: B


NEW QUESTION # 53
Which of the following is NOT required when performing weekly or monthly schedule updates?

  • A. Percent complete.
  • B. Actual finish of activities.
  • C. Remaining duration of activities.
  • D. Original duration of activities.

Answer: C


NEW QUESTION # 54
What does the heavy, vertical line at "X" represent?

  • A. The status or data date.
  • B. International Date Line.
  • C. Change-over limits.
  • D. Delay fault line.

Answer: A


NEW QUESTION # 55
Determine the correct formula and date for the late start for the Activity 11001:

  • A. LF.11001 - Dur.11001 -> 01-16-04.
  • B. LF.11001 - 27 days + 1 day -> 01-14- 04.
  • C. LF.1001 + DUR.10001 -> 01-14-04.
  • D. LF.10001 + 1 day -> 01-16-04.

Answer: D


NEW QUESTION # 56
Which statement is true?

  • A. Where compensability cannot be established, excusability is a given.
  • B. Where compensability can be established, excusability is assumed.
  • C. Where compensability can be established, excusabltity cannot be assumed.
  • D. Where compensability cannot be established, excusability is assumed.

Answer: D


NEW QUESTION # 57
What owner action could have mitigated the late completion of the project?

  • A. Self-perform more of the work.
  • B. Prepare better structural steel drawings.
  • C. Use a procurement agent to monitor and expedite equipment deliveries.
  • D. Hire a more senior project manager.

Answer: C


NEW QUESTION # 58
In a "crashed" schedule, which is a chain of activities that precede activity 2004?

  • A. 2001, 2002, 2003, 2007
  • B. 1001, 2001, 2002, 2003
  • C. 1001, 2002, 2003
  • D. 1001, 2002, 2002, 2003, 3001

Answer: B


NEW QUESTION # 59
If all other work proceeds according to the Baseline plan, how many times will the critical path change?

  • A. 2.
  • B. 3.
  • C. Does not change.
  • D. 1.

Answer: C


NEW QUESTION # 60
Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?

  • A. 12-18-03 and 4 days of float
  • B. 12-17-03 and 4 days of float
  • C. 12-27-03 and 24 days of float
  • D. 12-18-03 and 25 days of float

Answer: B


NEW QUESTION # 61
......